8/20/23 – Battleship Texas Update
Posted by Battleship Texas Foundation on August 20, 2023
DRY DOCK TOURS
Dry Dock Tours return in September! Tours are Sundays only, until December 17th. Click below for more information!
SHIP REPAIRS
Deck Repairs
GC’s yard workers have concluded repairing the deck on the ship’s Signal Bridge and have begun working on the deck above, the Navigation Bridge. A part of the deck repairs includes sand blasting the underside of the underside and throwing on a coat of primer.
Aft Fire Control Tower
Work continues in the AFCT as the old grating that was installed in 1988 has been completely removed and replaced with a steel deck. Small repairs to the bulkhead are currently ongoing as the plan is to have it look as it did in 1945.
Torpedo Blisters
The torpedo blister modules are produced in the fabrication shop and are transported to the dock where they will be attached to the ship’s hull. There are currently three more torpedo blister modules under construction in the shop!
The new torpedo blisters are a slightly different design and square off at the bottom below the waterline. This design change will make the new blisters easier to maintain, increasing their longevity.
Coating
Yes, the inside of the blisters, and the ship’s hull will be coated to protect against possible corrosion.
Hull
As work continues moving aft, any holes in the ship’s original hull are being repaired. New plates are added to thinner areas and smaller holes are welded up. The ship’s hull is being primed temporarily as the repairs are made.
Leak Testing
Yes, all welds are being tested for leaks. This is done via vacuum box, dye penetrant or magnetic flux depending on the area.