Close
  • View Our Store
  • Latest News
  • News

    9/10/23 – Battleship Texas Update

    Posted by Battleship Texas Foundation on September 10, 2023

    Featured image for Post named `9/10/23 – Battleship Texas Update`

    DRY DOCK TOURS

    Dry Dock Tours return in September! Tours are Sundays only, until December 17th. Click below for more information!

    Dry Dock Tour

    SHIP REPAIRS

    Torpedo Blisters

    The new torpedo blisters are a slightly different design and square off at the bottom below the waterline. This design change will make the new blisters easier to maintain increasing their longevity. The new torpedo blisters are now completely plated up.

    Coating

    The inside of the blisters, and the ship’s hull will be coated to protect against possible corrosion.

    Hull

    As work continues moving aft, any holes in the ship’s original hull are being repaired. New plates are added to thinner areas and smaller holes are welded up. The ship’s hull is being primed temporarily as the repairs are made.

    Leak Testing

    Yes, all welds are being tested for leaks. This is done via vacuum box, dye penetrant or magnetic flux depending on the area.

    Super Structure Repairs

    Structural, decking, drainage, and other repairs have begun on the ship’s foremast and aft control tower as part of the Save America’s Treasures grant project.

    Deck Repairs

    Gulf Copper’s yard workers have concluded repairing the deck on the ship’s Signal Bridge and have begun working on the deck above, the Navigation Bridge. A part of the deck repairs includes sand blasting and priming the underside. Scaffolding is in place around the foremast for this work.

    Aft Fire Control Tower

    Work continues in the AFCT as the old grating that was installed in 1988 has been completely removed and replaced with a steel deck. Small repairs to the bulkheads are currently ongoing, as the plan is to have it look as it did in 1945.