    The ship is still moored along Pier D in Gulf Copper Shipyard where their people are hard at work. It cannot be understated how much we appreciate their efforts in this undertaking as we know the work before them has not been easy.

    FREQUENTLY ASKED QUESTIONS

    What’s Next?

    Battleship Texas will remain at Gulf Copper Shipyard for until her new home is ready for her. Additional steel work, removal and replacement of the ship’s deck, and superstructure/aft fire control restoration will continue. And painting the topsides!

    Touring?

    The Battleship Texas Foundation is working on new touring opportunities before the ship reopens.

    Reopening?

    There is a lot to be done before the ship is ready for touring at its new home in Galveston, Texas. Reopening is projected to happen sometime in 2025 or 2026.

    Missing Guns?

    The ship’s anti-aircraft guns are currently undergoing restoration. The guns and gun directors will be replaced once their restoration is complete. Five of the ship’s six 5″ guns have already been reinstalled.

    SHIP REPAIRS

    Deck Repairs

    The pine decking on the ship’s bow and superstructure deck has been removed. Workers have started to sandblast the steel deck and make any necessary repairs. Once those repairs conclude, the steel deck will be properly coated and a pressure treated pine decking will be laid. Yes, some of this wood is being saved to produce items to raise funds. Some deck wood items are already available in the ship’s store.

    Smoke Stack Repairs

    The ship’s smoke stack is being repaired so that it becomes watertight. Both the whistle piping and siren will be added when repairs conclude.

    Drainage Repairs

    The ship’s drainage system is being restored. This will protect the ship from rain water intrusion and greatly extend the life of the other top-side repairs that are in progress.

    Aft Fire Control Restoration

    The ship’s aft fire control tower is looking great! The mullions for the windows are fitted, floater net baskets added, and more. These repairs and additions will help return the ship to its 1945 appearance.

    Turret Watershed Repairs

    The turret water sheds are being removed from the turrets to be repaired. The watersheds keep water out of the gaps between the turret and barbette. There is a considerable amount of corrosion between the layers of steel that needs to be addressed before the ship is repainted. The watersheds will be reinstalled once those repairs are complete.

    Radar Top Mast

    The radar top mast has been removed from the ship’s main mast and has largely completed the required repairs. There are a few things which need to be done before it gets its final coat of paint and is reattached to the ship.

    Main Mast

    The deck on the ship’s main mast is being repaired and replaced in certain areas. Gun mounts are also being added back.